|
JAC Style guide: template
PATT ITAC Report for Semester 97B
1. Introduction
This document details the allocations for telescope time made
by the ITAC for the semester 97B (1st August 1997 - 31st January
1998).
2. Allocations
The individual partner TAGs hold meetings in their respective
countries prior to the PATT session to assess applications deemed
by the JCMT Board rule to be from their own country. At these
meetings informal numbers of shifts are nominated for each application
in a priority order. The Chairpersons of each TAG bring their
respective lists to the PATT where the ITAC combine the awards,
include discussion of the engineering and commissioning requirements,
and assess the International applications. The final allocations
of shifts are made by the ITAC.
Applications to be considered
UK status 101
Canadian status# 46
Netherlands status 31
International status* 25
University of Hawaii 14
TOTAL: 217
# two Canadian long-term carry-overs have not been included in
this total.
* this total includes 3 SBI applications through the CSO system.
The PATT meeting was held at the ROE, Edinburgh, UK on 28th &
29th July 1997.
It should be noted that if the PI on an application is a JCMT
staff member based in Hilo, then the application is assessed by
the appropriate national TAG. However, by Board rule, International
status is given to any application where the only named collaborator
from any partner country is a JCMT staff member. International
applications are assessed by the ITAC members at their meeting.
Time Available (in 16-hour nights)
No. of night set aside in semester 97B 183.0
Engineering & Commissioning 33.5
Set aside for SCUBA2! 30.0
University of Hawaii (10%) 11.5
Director's discretionary use 4.0
Available for PATT science: 104.0
! this total then concludes the SCUBA 2nd round (SCUBA2) allocations.
The above table indicates the order in which nights are removed
from the total available for the semester. Semester 97B covers
a winter period from 1st August 1997 through 31st January 1998
inclusive. The JCMT is closed on Christmas Eve.
Awards (in 16-hour nights)
UK status 51.625
Canadian status 23.500
Netherlands status 18.750
International status 10.125
University of Hawaii 11.500
TOTAL allocation: 115.500
3. Designated Service time
Allocations for this semester are:
CDN = 5.0 shifts allocated;
NL = 0 shifts allocated (but all Netherlands time is flexibly
scheduled);
UK = 0 shifts allocated (but several are on the Ukflex listing)..
4. Non-standard Instrumentation
There is no non-standard instrumentation scheduled for this semester.
Instrument distribution
A-band 15%
B-band 16%
C-band 6%
SBI (mainly B-band) 6%
SCUBA 57%
5. Applications with Long-Term Status
L/M/96A/C08 was given a further 4 night shifts in 97B to complete
the comet observations. The student thesis project, M/Y/C05 was
also awarded a further 1 shift which should conclude this project.
6. Short Baseline Interferometry
After negociation amongst the SBI team it was decided that a session
of no longer than 8 days would be possible in early November.
The constraints were a combination of the availability of the
personnel involved, and the scheduling restrictions on both the
CSO and the JCMT. One whole night of setup time was required which
left 7 whole nights of observing time to be divided equally between
ITAC and CSO applications.
7. Use of Daytime Periods
The comet Hale-Bopp remains a daytime object until late September.
Then it is observable using morning shifts until early November
when it is too far South to be observable with the JCMT. Several
daytime shifts have been allocated to the comet watch teams with
the same restraints that were imposed during previous semesters
(see details in ITAC Report to the previous Board meeting).
8. Engineering & Commissioning
Once again the large amount of time set aside for SCUBA 2nd round
observing (SCUBA2) and for the commissioning of instrumentation
(RxA3i, RxB3 upgrade, SCUBA interim polarimeter and RxW), all
other E&C tasks have been kept to a minimum for the semester.
Commissioning of the antenna and instrumentation continues, with
periods required a) to characterise and improve the surface via
metrology and beam map measures, b) to monitor the antenna performance
and tracking through pointing and inclinometry runs, and c) to
measure receiver performances and efficiencies.
Time has been allocated for commissioning of RxA3i, RxW and for
the SCUBA interim polarimeter according to the commissioning plans
made available by the instrument builders. Several shifts have
also been left open for upgrading the mixers in RxB3.
9. SCUBA 2nd Round (SCUBA2)
A total of 60 shifts were set aside from the allocation for semester
97A for flexibly queue-scheduling SCUBA observations. A total
of about 120 shifts of SCUBA2 time had been awarded and therefore
the outstanding 60 shifts have been set aside from semester 97B
to complete these queues. The SCUBA2 queues will not be carried
on beyond the end of semester 97B. All applicants with proposals
currently in the SCUBA2 queues have been informed of this procedure.
10. Fallback Programmes
A number of applications have been approved by the ITAC to be
included in the schedule should any of the instrumentation fail
to meet their delivery schedules. The commissioning time set aside
for these instruments will be apportioned according to the partner
funding ratio after 10% has been given to the University of Hawaii.
Applicants on these fallback programmes will be informed by the
JCMT Scheduler when/if their time is to be scheduled.
In addition, there are numerous heterodyne applications set aside
to be included as fallback for the SCUBA2. These fallbacks continue
to be done in serviced mode by JCMT staff.
11. The UKflex System
The UK TAG actually only allocated time to 77.45 shifts of its
final allocation of 103.25 shifts. The outstanding 25.8 shifts
were designated as UKflex time. A selection of heterodyne A- and
B-band applications with high scientific ratings were placed on
the UKflex list in priority order and with a nominal time allocation.
The intention is that each high-frequency allocation be extended
by a shift or two of UKflex time thus increasing the chance of
obtaining suitable weather to complete the high-frequency program.
Under weather conditions unsuitable for the high-frequency observing,
the current observers or staff scientist would undertake observations
from the UKflex list in serviced mode. Successful applicants on
the UKflex list have been informed that they have to submit complete
templates for their observations but that there is no guarantee
that any part of their program will be done during the semester.
12. Electronic Submission
Various electronic submission procedures have been tried at other
PATT facilities with varying degrees of success. Due to the international
status, and because there are currently 3 different collection
locations for applications to the JCMT, we have so far kept out
of these experiments.
The Netherlands already implement a very successful electronic
submission scheme. For the current semester 97B round all Netherlands
applications were accepted electronically and made available to
Hawaii via FTP. The Canadian community is encouraged to submit
electronically and, although the numbers are increasing, the majority
of applications are still sent as hardcopy.
A system has now been setup in Hawaii that resembles the HST electronic
submission procedures. This software suite is under licence from
the STScI. For semester 98A, International applicants were encouraged
to submit their proposals directly to a designated account at
the JAC. If this trial is successful then it will be expanded
to include the UK community and also to link to the Canadian and
Netherlands schemes. Further details on the electronic submission
system is contained in a separate Board paper.
13. Procedures for Semester 98A
The deadline for for semester 98A (1st February through 31st July
1998) applications was 30th September 1997 for ALL applicants.
This deadline encompasses applications for all available instrumentation
on the JCMT (RxA2, RxB3, RxC2, and SCUBA). There is also likely
to be an SBI run during the semester. It is not possible to apply
for features specific to either RxA3i or to RxW (ie: no D-band
observations) since these instruments will not have been commissioned
prior to the ITAC meeting in early December. Due to the special
nature of the SCUBA interim polarimeter, it may be available for
use during semester 98A provided it successfully passes its commissioning
tests.
Last Modification Date 1997/03/12 - Last Modification Author:
Graeme Watt (gdw)
|